Material Requirement Planning defines techniques based on master production schedule and information from inventory records to determine the requirement and scheduling of each material item.
Let us see how to check the new MRP Live planning run in the SAP S/4 HANA Enterprise Management system. Navigate to SAP Fiori Launchpad −
Search for application - Display Multilevel BOM Explosion and open Fiori app.
In the next window, you have to enter the following details −
Choose Execute (F8)
Open Fiori app Display Routing for the material and Plant.
Click Operation Overview to determine which operations (make a note of the operation numbers and descriptions) are executed at which work center.
To perform live MRP run, navigate to app Schedule MRP Runs and double-click on app to open app Schedule MRP Runs.
In the next window, Fiori app Schedule MRP Runs choose New, to create a new job. Change the description to MRP live Group.
Under scheduling options, you can add a schedule to define MRP Live run and remove the Recurrence flag. Choose OK.
Enter plant and MRP controller. Don’t change the control parameters and click the Schedule button. Next is to select app Monitor Stock / Requirements List for your material and plant to analyze your planning result.
In the next window, you have to enter your material and plant and press Enter. Note that you would also be able to access this app via /NMD04 transaction.