In SAP Project System, you can define the person responsible for Work Center. To define a responsible person, you need to enter person responsible Id and descriptive name of the person responsible for managing the work center.
To specify a person responsible for work center, navigate to the following path in SAP Easy access.
Step 1 − SPRO → IMG → Project System → Structures → Operative structure → Network → Work Center → Specify person responsible for work center
Step 2 − In the next window for Person Responsible for Work center, click New Entries.
Step 3 − In the next screen, you have to enter the following details −
Plnt − Enter the plant key that you want to assign person for work center.
Pers. Respons − In this field, enter the person responsible for work center ID
Person responsible for work center − Descriptive name of person responsible for managing work center.
Step 4 − Once you enter all the details, click the save button at the top.