You can create variance measures such as variance to budget, variance to forecast, and forecast variance to budget. You can also analyze the finance data based on these measures.
Create Variance to Budget Sum measure (VTB Sum) as follows −
VTB Sum:=[Budget Sum]-[Actual Sum]
Create Variance to Budget Percentage measure (VTB %) as follows −
VTB %:=IF([Budget Sum],[VTB Sum]/ABS([Budget Sum]),BLANK())
Create a Power PivotTable as follows −
Create Variance to Forecast Sum (VTF Sum) measure as follows −
VTF Sum:=[Forecast Sum]-[Actual Sum]
Create Variance to Forecast Percentage measure (VTF %) as follows −
VTF %:=IF([Forecast Sum],[VTF Sum]/ABS([Forecast Sum]),BLANK())
Create a Power PivotTable as follows −
Create Forecast Variance to Budget Sum (Forecast VTB Sum) measure as follows −
Forecast VTB Sum:=[Budget Sum]-[Forecast Sum]
Create Forecast Variance to Budget Percentage (Forecast VTB Percentage) measure as follows −
Forecast VTB %:=IF([Budget Sum],[Forecast VTB Sum]/ABS([Budget Sum]),BLANK())
Create a Power PivotTable as follows −